Permits Pulled for Broadband as of 6/30/2025
- WI 57 Clark Lake Rd northeast north of County Road T- 8/15/25-11/15/25
- WI 57 from the downtown area up to the curve before Valmy 8/15/25-11/15/25
- WI 42 – new poly pad placement in the ROW south of W Town Line Road 6/20/25-12/31/25
- WI 57- from St. Nick’s Tree Farm through Valmy 6/20/25-12/31/25
- WI 42 – north of Clark Lake Rd to south of Fish Road 6/20/25-12/31/25
- Also a new County permit for work over near County Road HH 7/15/25-11/15/25
- Work starting at 5238 Bay Shore Drive – bore and place new strand to existing poles
- Work starting at 5504 County Rd HH - replace poles and place new strand to existing
- Work starting at 6050 Old County OR – bore and place 2” inner duct and place new strand to the existing poles
- Work starting at 3879 Whitefish Bay Rd/County T bore and place new strand to existing aerial cables
- Work to start at 4436 Whitefish Bay Rd/County T bore and place aerial fiber to existing cable and pull new fiber through existing
- Work to start at 4305 Clark Lake Rd /County Hwy WD bore and place innderduct and 4” pvc
AT&T Kickoff - June 6, 2025
AT&T helping the Door County Community! 10.24.24 - ATT Laptop Distro BGC Sturgeon Bay PR
Letter to the Town of Sevastopol Residents from AT&T and the Town. AT&T Sevastopol Letter
AT&T Vehicles that you will see in your neighborhoods.
Additional Broadband information